What makes an industrial lithium-ion battery pack safe, stable and long-lasting? It is not only about high-quality cells, but also strict standardized assembly and multi-round performance verification. Every qualified Prolaker lithium-ion battery pack must complete the full set of assembly and testing procedures as below.
Step 1: Pre-assembly Inspection & Module Preparation
Before assembly, the enclosure will pass incoming quality inspection. Technicians clean the enclosure interior and lay insulating mats. Cells are assembled into complete modules, followed by module fastening. All connecting plates, steel straps, end-plates and spacers are assembled to form stable battery modules, ensuring mechanical stability inside the pack.
Step 2: Wiring & Component Installation
This phase covers core mechanical and electrical assembly work:
1. Fit connectors, collection harnesses and power cables.
2. Strict torque control: Tight all bolts and carry out torque measurement & re-check, to avoid loose connections under vibration.
3. Complete wire-sequence inspection to prevent wiring errors.
4. Install BMS (Battery Management System), PDU power distribution unit, fuses, insulators, lifting rings and external components.
5. Mount battery top cover and charge-discharge connectors, then run insulation test for total positive / total negative terminals and charge-discharge connectors.
PDU unit features uniform IP67rated interfaces, angled aviation connectors and optimized cable routing, improving reliability and simplifying later maintenance.


Step 3: Power-on & Cycle Performance Testing
Every finished pack goes through standardized charge-discharge cycle testing, which is critical to validate real-world performance:
1. Charge with 0.5C constant current; constant-voltage set as 3.65V × cell series quantity, record BMS upper-limit protection parameters.
2. Stand for 5 minutes after full-charge.
3. Discharge with 0.5C constant current, cut-off voltage set as 2.75V × cell series quantity, record BMS lower-limit protection conditions.
4. Stand another 5 minutes.
5. Re-charge to SOC 60%-70% for storage status before delivery.
During testing, technicians record internal resistance, voltage difference and protection trigger points. The pack will be qualified only if it meets our acceptance criteria:
· Discharge capacity higher than nominal capacity
· Voltage difference ≤200mV under key working conditions
· Correct trigger for over-charge, over-discharge and SOC protection (power-off at 10% SOC)
Step 4: Final QC & Warehousing
After passing all electrical tests:
✅ Self-check and cross-verify against official specifications & documents
✅ Complete power-supply function testing
✅ Paste nameplates and identification labels
✅ Appearance inspection
✅ Qualified products go into warehouse for delivery; non-conforming units return to previous process for rework.

Why These Strict Procedures Matter
Prolaker sticks to full-process control from enclosure incoming inspection to final cycle testing. Each battery pack is fully tested, not only lab-sample tested.